  Pool Details 51.5m x 25m Competition pool with a movable floor and traversable boom 25m x 21m Diving pool, with movable floor.
Client Sunderland City Council
Completion 2007
Construction Cost £20,000,000
Our Role Water treatment on all pools, movable floors and booms and diving pool air cushion system.
 
Design Team
 
line
  Architect Red Box
Aquatic Consultant Devin
Structural Engineers Arup
M & E Engineers Arup
Quantity Surveyors Davis Langdon